Real-world experience is one of the most valuable tools when planning a metering programme. The following case studies highlight the benefits achieved and challenges overcome in recent deployments across different communities. They illustrate how metering has delivered tangible outcomes, such as reduced demand, deferred infrastructure investment, and improved equity, while also capturing lessons learned to refine future rollouts. Together, these examples provide practical insights that can help shape a more effective, efficient, and community-supported metering programme.
Nelson City Council completed its universal metering roll-out between 1996 and 1999 and switched on volumetric billing in July 1999, making every household’s consumption visible and billable.
The programme drove a 37 % reduction in peak-day demand, virtually eliminated the need for seasonal watering restrictions, and pushed the requirement for a new water source more than 50 years into the future.
Between 1999 and 2001 Tauranga City Council rolled out universal residential water meters, switching on volumetric billing in 2002.
The impact was immediate and sustained: peak-day demand fell by roughly 30 percent and average-day demand by about 25 percent. It took 17 years, despite the network serving an extra 40,000 residents, before consumption crept back to pre-metering levels, summer watering restrictions were again needed, or a third source had to be developed.
The metering programme also delivered a bonus benefit: noticeable reductions (7-10%) in dry-weather wastewater flows, pointing to less wastewater generation across the network.
Kapiti Coast District Council installed universal residential water meters in 2014. Peak-day demand dropped by 26%, average-day demand by 21 %, and dry-weather wastewater flows by 5–8 %.
Kapiti identified that following the introduction of volumetric charging 97% of the 443 leaks found during meter installation had been fixed achieving a 90% reduction in water use.
Additionally a 70% decrease in water use was recorded for the 670 high (>2,000 litres/day) water users identified during the trial readings period.
The NZ $9.8 million metering programme deferred about NZ $36 million in early source-augmentation and storage projects by roughly 40 years. Since metering was introduced, the district has not needed summer water restrictions.
Christchurch applies an volumetric allowance for residential customers and charges for excess water use per metre cubed there after. The estimates savings are based on modeling done by Christchurch based on this system.
New Plymouth’s universal-metering programme was about three-quarters complete at the end of 2024/25, with 19,600 of the planned 25,500 residential meters (c.77 %) already in service. The water metering data has revealed and repaired 466 private-side leaks, including a single property that was losing 60 m³ per day, roughly 200,000 cups of tea, on its own.
The city is now saving c.1.09 ML of treated water every day, enough to meet the needs of around 4,000 residents. These demand reductions let the council postpone a $4 million pump-station upgrade by at least ten years, freeing capital and operating expenditure for other network priorities.
Below are key lessons distilled from past universal water-metering projects and national experience.
Establish a clear business case first, Build the meter programme around deferring or downsizing new sources, storage and treatment assets or avoiding abstraction consent breaches; include reduced OPEX, consent surety and equity benefits in the NPV.,
Communications & politics, Face-to-face sessions with community “influencers” (Rotary, Greypower, etc.) were the most effective counter to misinformation; allocate specialist comms capacity.,
Re-evaluate meter technology each cycle. Mechanical meters met past cost targets, but falling prices and longer battery life mean smart-meter options now warrant a fresh business-case test.
Keep communications simple and timely for customers, using plain language to explain what will happen, when, and why; give clear advance notice of key milestones such as meter-box installation, trial readings, and the start of billing, and always link each update back to the core message about why metering is being introduced.
Have strong, well-defined policies on public versus private responsibilities, setting the ownership boundary, detailing council duties for meters and their maintenance, and customer obligations for downstream plumbing and leak repair; embed these in the bylaw.
Treat it as a logistics project, Treat the roll-out as thousands of micro-work-sites: resource a dedicated install/liaison crew, automate the tracking of progress and quality assurance and resolve access or reinstatement issues fast.,
Getting the charging right matters, A 50 / 50 split between fixed and volumetric revenue has proved enough to drive c.25 % peak-day reductions while limiting bill-shock and protect revenue. Consider “entitlement water” carefully as it doesn’t provide a strong enough incentive for change
Trial reads before billing, send sample invoices for 3-6 months to let households find leaks and adapt usage, and to debug billing systems.,
Effective customer engagement can be resource intensive. Extra call-centre and field staff, plus face-to-face sessions with community influencers, are critical to manage queries and counter misinformation during roll-out.
Leak detection & data, Universal metering quickly pinpoints large private leaks and cuts dry-weather inflows; Marlborough, Kapiti and New Plymouth saw major water savings.,
Price stability, Budget for meter-driven demand drops; smooth initial revenue shocks. Adopt a policy that spreads any first-year surplus or deficit over several years to keep charges stable.
Reductions in dry weather flows in the wastewater system of up to 10 % have been experienced in the programs.
The New Zealand Infrastructure Commission has also undertaken work in this area commissioning a report[1] on the lessons and perspectives of introducing water metering that provides valuable insights many that have been incorporated into this White Paper.
The 2017 Good Practice Guide by Water New Zealand, "Water Metering of Customers on Reticulated Supplies," offers comprehensive guidance on various engineering aspects, and best industry practices.. It informs policies that support clear communication with communities about responsibilities and costs, such as who pays for what—whether it be the individual or the Council—and how the system will be managed. We suggest referring to this document for much of the engineering details necessary in the establishment, rollout, operation and maintenance of a program.